CHARGING STATIONS FOR ELECTRIC VEHICLES

ITALIAN RULES – Information Sheet – May 2024

electric vehicle charging station

Authors: Claudio Palmieri & Chiara Cremona

EUROPEAN REGULATIONS

EU Regulation 2023/1804, Sept. 13, 2023, on the deployment of alternative fuels infrastructure (AFIR)

  • Requirements for user information, data provision and payment methods applicable to publicly accessible charging pools;
  • Mandatory national targets for sufficient infrastructure for light-duty and heavy-duty electric vehicles;
  • common technical specifications (Annex II)

Technical specifications for the supply of electricity for road transport

Normal power recharging points for motor vehicles
alternating current (AC) normal power recharging points for electric vehicles shall be equipped, for interoperability purposes, at least with socket outlets or vehicle connectors of Type 2 as described in standard EN 62196-2:2017.

High-power recharging points for motor vehicles:
— direct current (DC) normal power recharging points for electric vehicles shall be equipped, for interoperability purposes, at least with connectors of the combined charging system ‘Combo 2’ as described in standard EN 62196-3:2014;
— alternating current (AC) high-power recharging points for electric vehicles shall be equipped, for interoperability purposes, at least with connectors of Type 2 as described in standard EN 62196-2:2017;
— direct current (DC) high-power recharging points for electric vehicles shall be equipped, for interoperability purposes, at least with connectors of the combined charging system ‘Combo 2’ as described in standard EN 62196-3:2014.

Recharging points for L-category motor vehicles:
The publicly accessible alternating current (AC) recharging points reserved for L-category electric vehicles up to 3,7 kW shall be equipped, for interoperability purposes, with at least one of the following:
(a) socket-outlets or vehicle connectors of Type 3A as described in standard EN 62196-2:2017 (for Mode 3 charging);
(b) socket-outlets compliant with standard IEC 60884-1:2002 + A1:2006 + A2:2013 (for Mode 1 or Mode 2 charging).

Normal-power recharging points and high-power recharging points for electric buses:
— alternating current (AC) normal-power recharging points and high-power recharging points for electric buses shall be equipped at least with connectors of Type 2 as described in standard EN 62196-2:2017;
— direct current (DC) normal-power recharging points and high-power recharging points for electric buses shall be equipped at least with connectors of the combined charging system ‘Combo 2’ as described in standard EN 62196-3:2014.

Contact interface automated device for electric buses on conductive recharging in mode 4, in accordance with standard EN 61851-23-1:2020, shall be equipped at least with mechanical and electrical interfaces, as defined in the standard EN 50696:2021, concerning:
— automated connection device (ACD) mounted on the infrastructure (pantograph);
— automated connection device (ACD) mounted on the roof of the vehicle;
— automated connection device (ACD) mounted underneath the vehicle;
— automated connection device (ACD) mounted on the infrastructure and connecting to the side or on the roof of the vehicle.

ITALIAN FRAMEWORK LEGISLATION

LEGISLATIVE DECREE December 16, 2016 , no. 257, Regulations implementing Directive 2014/94/EU of the European Parliament and of the Council of October 22, 2014, on the establishment of an alternative fuels infrastructure.

– Applicable for aspects not covered by EU Regulation 2023/1804 –

  • national strategy
  • specific provisions for the supply of electricity for road transport:
    • publicly accessible charging points
    • Charging points not accessible to the public
    • regulation and attribution of competences to ARERA for the technical and punctual rules necessary to facilitate the connection of recharging points, whether public or private access, to the electricity distribution network
  • information obligations to users
  • measures to facilitate the establishment of charging points –> v. URBAN PLANNING AND BUILDING LEGISLATIONS .

TECHNICAL STANDARDIZATION

Law March 1, 1968 no. 186 and Art. 17-quater Normalization of Decree Law June 22, 2012 no. 83, Urgent measures for the country’s growth.

The construction and installation of electric vehicle charging infrastructure networks that meet the standards of the European and international standardization bodies International Electrotechnical Commission (IEC) and Comitè Européen de Normalisation Electrotechnique (CENELEC) are permitted.

The technical standards applicable to the charging infrastructure are numerous, constantly evolving and not only electrical. Among the most important are the following

Standards for charging systems
IEC 61851-1 Electric vehicle conductive charging system – Part 1: General requirements.
IEC 61851-21 Electric vehicle conductive charging system – Part 21-1 Electric vehicle on-board charger EMC requirements for conductive connection to AC/DC supply.
IEC 61851-22 Electric vehicle conductive charging system – Part 22: AC electric vehicle charging station.
IEC EN 61851-23 Electric vehicle conductive charging system – Part 23: DC electric vehicle charging station.
IEC 61851-24 Conductive charging of electric vehicles Part 2A: Digital communication between DC charging station and electric vehicle for charge control.

Standards for connectors
IEC 62196 Plugs, socket-outlets, vehicle connectors and vehicle inlets – Conductive charging of electric vehicles.
CEI 69-6 Unification sheet of plug sockets for connecting road electric vehicles to the power grid.

Standards for safety of charging systems including installation conditions
EC Marking Low Voltage Directive 2014/35/EU LVD – “Low vottage directive”.
EC Marking Directive 2014/30/EU EMC – “Electromagnetic compatibiLity directive”.
IEC 61000-6-2 Electromagnetic compatibility (EMC) – Part 6-2: Generic standards – Immunity standard for industrial environments.
Electromagnetic compatibility (EMC) – Part 6-3: Generic standards – Emission standard for equipment in residential environments.
CEI 20-106 Electric cables with cross-linked insulation not propagating flame, with rated voltage not exceeding A50/750V intended for charging electric vehicles.
IEC 60529 Degrees of protection provided by enclosures (IP Code).
IEC 62262 Degrees of protection provided by enclosures for electrical equipment against external mechanical impacts (IK code).
CEI EN 50102 (CEI 70-3) Characteristics of low-voltage switchgear enclosures.
IEC 61439-2 Low-voltage switchgear and controlgear assemblies – Part 2: Power switchgear and controlgear assemblies.
IEC 61439-7 Low-voltage switchgear and controlgear assemblies – Part 7: Assemblies for specific applications such as marinas, camping sites, market squares, electric vehicle charging stations.
CEI 6A-8 Variant 5 Part 7, Section 722 Power supply for electric vehicles.
CEI 0-21 Special requirements for installations intended for electric vehicle charging stations.

Standards for communication systems between vehicle and charging stations and between charging stations and the electric grid
IEC 61850 Communication networks and systems for power utility automation.
ISO/IEC 15118 Road vehicles – Vehicle to grid communication interface.
ISO/IEC 14443 Cards and security devices for personal identification – Contactless proximity objects.
Other non-electrical matrix standards: SAE J2847, SAE J2836, SAE J2293-2.

URBAN PLANNING AND BUILDING LAW

Article 57 simplification of rules for the construction of electric vehicle charging points and stations, Decree Law July 16, 2020 no. 76, on urgent measures for simplification and digital innovation.

  • Charging infrastructure can be implemented:
    • (a) in public and private areas and buildings, including those of public housing
    • (b) on private roads not open to the public
    • (c) along public and private roads open to the public
    • (d) in rest areas, parking lots and facilities, both public and private, that are open to the public
  • In cases (a) and (b) electric vehicle charging is considered a service and not a supply of electricity
  • Obligations related to the manner of realization and use for public infrastructure (cases (c) and (d) of the first point ):
    • Technical and Safety Standards v. TECHNICAL STANDARDIZATION
    • Traffic Code
    • facilities located along public roads and in parking areas must be accessible to all users in a non-discriminatory manner
  • Obligations related to the manner of realization for private infrastructure (cases (a) and (b) of the first point ):
    • compliance with regulations for the construction of electrical installations, with particular reference to the obligation of declaration of conformity and electrical design, where necessary, according to applicable laws –> for Technical and Safety regulations see. TECHNICAL STANDARDIZATION
    • Traffic Code
  • Building Permit, Public Charging Infrastructure Permits and Related Exemptions:
    • the installation of public charging infrastructure does not require a building permit and is considered free construction
    • applications for the occupation of public land and the construction of recharging infrastructure must be submitted to the road-owning entity, which will issue the permit within 30 days. Procedures are subject to the simplified application requirement, and the assessing agency issues a construction and public land occupation permit measure for recharging infrastructure, which has a minimum duration of 10 years, and a measure of unlimited duration, in the name of the grid operator, for related connection works
    • municipalities may allow, even free of charge, the construction and management of charging infrastructure to public or private entities, based on competitive procedures. Interested parties can still apply to the municipality for permission to build infrastructure. Municipalities may reduce or exempt the fee for charging points that use certified renewable energy. The public land occupation fee is calculated only on the space occupied by infrastructure, not on parking stalls. If the conditions for fee reduction or exemption are not met, municipalities may require retroactive payment of the fee and apply a surcharge of up to 30 percent
    • exemption from the stipulation of acts of submission
    • small and medium-sized enterprises are exempted from submitting the certified report of commencement of activities by subtracting for the construction of electric vehicle charging infrastructure
  • Other obligations:
    • obligation of substitute declaration of absence or presence of interference with telecommunication lines and compliance with electrical standards
    • concessions for service areas and the renewal of existing ones conditioned on the service areas being equipped with charging stations

Paragraph 1-bis of Art. 4, adoption of general criteria, calculation methodology and energy performance requirements, of Legislative Decree August 19, 2005 no. 192 on the Implementation of Directive (EU) 2018/844, amending Directive 2010/31/EU on the energy performance of buildings and Directive 2012/27/EU on energy efficiency, Directive 2010/31/EU, on the energy performance of buildings, and Directive 2002/91/EC on the energy performance of buildings

  • Electric vehicle charging technology integration requirements:
    • in non-residential buildings of new construction or undergoing major renovation with more than ten parking spaces, at least one charging point shall be installed and provision shall be made for one charging point for every five parking spaces. In residential buildings, however, every parking space in indoor or adjacent parking lots must be prepared for the installation of charging stations
    • regardless of renovations and new construction, at least one charging point must be installed in nonresidential buildings with more than 20 parking spaces as of January 1, 2025. Small and medium-sized enterprises, buildings for which the building permit application is submitted by March 10, 2021, areas where the stability of the local network may be endangered by the required sewerage infrastructure, and all those properties where the cost of installation exceeds the cost of building renovation by 7 percent are exempted

Art. 17-quinquies, simplification of construction activity and right to charging points of Decree Law June 22, 2012 no. 83 urgent measures for the country’s growth.

Construction works for the installation of electric vehicle charging infrastructure in condominium buildings shall be approved by the condominium assembly, on first or second call, with the majorities stipulated in Article 1136, first, second and third paragraphs of the Italian Civil Code. In the event that the condominium refuses to take, or fails to take within three months of the request made in writing, the resolutions referred to in Paragraph 2, the condominium owner concerned may install, at his or her own expense, the devices referred to in said Paragraph 2, in the manner provided therein. The provisions of Articles 1120, second paragraph, and 1121, third paragraph, of the Italian Civil Code remain unaffected.

PRICE REGULATIONS

Article 57 simplification of rules for the construction of electric vehicle charging points and stations, Decree Law July 16, 2020 no. 76, on urgent measures for simplification and digital innovation.

The Regulatory Authority for Energy Networks and Environment (ARERA) – https://www.arera.it/ – operates regulatory interventions on

  • network tariffs and tariff components with respect to electric vehicle charging for residential customers
  • network tariffs and tariff components with respect to electric vehicle charging in publicly accessible locations
  • the costs and methods of connecting charging points
  • the connection times to the charging points

INCENTIVES

Recharging points incentive for businesses and professionals:

  • due date: June 20, 2024
  • Purchase and installation of charging infrastructure with a total value of less than 375 thousand euros by companies
  • Purchase and installation of charging infrastructure by professionals with turnover not less than the value of the infrastructure and may not exceed 20,000.00 euros in the case of the professional’s flat-rate regime

PNRR:

  • Large-scale construction of public fast-charging points (on highways and in urban centers) and experimental charging stations with storage, with the aim of promoting the development of electric mobility –> https://www.mase.gov.it/pagina/investimento-4-3-installazione-di-infrastrutture-di-ricarica-elettrica-0
  • The investment consists of three lines of intervention:
    • Line A: Installation of rapid charging stations for electric vehicles on suburban roads of at least 175 kW;
    • Line B: Installation of fast charging stations for electric vehicles in urban areas of at least 90 kW;
    • Line C: Installation of pilot charging stations with experimental nature and energy storage.