Energy from renewable sources: Legislative Decree 190/2024 and reorganization of administrative procedures


Authors: Claudio Palmieri & Chiara Cremona

February 18, 2025

Energy from renewable sources

————————

On December 30, 2024, Legislative Decree 190/2024 entered into force about regulation of administrative regimes for the production of energy from renewable sources in implementation of Article 26, paragraphs 4 and 5, letters b) and d) of Law No. 118 of August 5, 2022 (Official Gazette, December 12, 2024, No. 291).

The Italian decree defines the administrative regimes for the construction and operation of energy production plants from renewable sources, for modification, enhancement, total or partial refurbishment of such plants, as well as for related works and essential infrastructures for the construction and operation of the same plants (Article 1, paragraph 1).

According to Article 1, paragraph 3, regions and local authorities in Italy must comply with the principles set out in the decree within one hundred and eighty days from its entry into force.

To simplify administrative procedures and ensure the maximum dissemination of energy production plants from renewable sources (Article 1, paragraph 2), the decree, in Article 6, has streamlined the types of administrative regimes for plants powered by renewable sources to three:

  • Free activity, whose interventions are listed in Annex A of the decree, divided into two sections for new constructions or interventions on existing plants.
  • Simplified enabling procedure (Procedura Abilitativa Semplificata – PAS), whose interventions are listed in Annex B, also divided into two sections for new constructions or modifications of existing plants.
  • Single authorization (Autorizzazione Unica – AU), whose interventions are listed in Annex C, divided similarly into two sections.

1. Evolution of Authorization Procedures: Before and After Legislative Decree 190/2024

Before the recent decree came into effect, the Italian regulatory framework for installing plants powered by renewable sources was characterized by multiple authorization regimes, often complex and fragmented.

The administrative regimes outlined in Article 4 of Legislative Decree No. 28/2011 included:

  • Notification to the Municipality for free building activities (Comunicazione al Comune per le Attività in Edilizia Libera – CAEL).
  • Certified declaration of commencement of works (Dichiarazione di Inizio Lavori Asseverata – DILA), where the property owner or holder of the property submitted a declaration to the Municipality with a technical report signed by a qualified designer.
  • Simplified enabling procedure (Procedura Abilitativa Semplificata – PAS), requiring submission of a detailed technical report 30 days before the start of work.
  • Single authorization (Autorizzazione Unica – AU), involving a conference of services between the competent authorities, with the final authorization granted by the region or delegated provinces, or for plants with a thermal capacity of 300 MW or more, by the Ministry of the Environment and Energy Security.

Pursuant to Article 15, paragraph 2, for ongoing procedures, those for which the completeness check of the submitted documentation has been completed by the date of entry into force of the new decree the aforementioned administrative regimes shall continue to apply. However, the proponent retains the option to choose the application of the new provisions.

2. Analysis of the New Procedures Introduced by the Decree

2.1 Free activity interventions (Article 7 – Annex A)

Unlike the previous system, interventions carried out under free activity are not subject to obtaining permits, authorizations, or administrative approvals. The proponent is not required to submit any notification, certification, or declaration to public administrations.

However, interventions must be compatible with approved urban planning instruments and regulations. If interventions are planned in areas subject to landscape constraints, prior authorization from the competent authority is required, which must be issued within 30 days of the request.

For interventions involving the occupation of non-anthropized land, a financial guarantee must be provided to ensure dismantling and restoration (Article 7, comma 7).

Examples of interventions listed in Annex A – Section I include photovoltaic solar plants under 12 MW integrated into existing buildings without altering their structure and agrivoltaic plants under 5 MW that allow for agricultural and pastoral activities.

2.2 Simplified enabling procedure (Procedura Abilitativa Semplificata – PAS) (Article 8 – Annex B)

The Simplified Enabling Procedure (PAS), which applies to interventions listed in Annex B, concerns projects that are not subject to environmental assessments.

Article 8, paragraph 2, specifies that if the proponent does not have availability of the surfaces for the installation of the plant, or if the interventions are not compatible with approved urban planning instruments and current building regulations, or if they conflict with adopted urban planning instruments, then Article 9 on authorization must apply.

Regarding the required timelines, Article 8, after stating in paragraph 6 that if the proposing party is not notified of an explicit rejection within 30 days from the submission of the project, the enabling title is considered finalized without conditions, distinguishes between:

  • Interventions requiring one or more approvals under municipal jurisdiction, for which the municipality must issue a decision within 45 days from the submission of the project. If this period expires without a response, the enabling title will be considered finalized without conditions (tacit approval).
  • Interventions requiring approval from authorities other than the proceeding administration, for which the competent municipality must convene a conference of services within 5 days from the project’s submission. If 60 days pass from the submission without a formal rejection of the conference’s outcome or a well-founded objection from an administration responsible for environmental, landscape-territorial, cultural heritage, public health, or safety protection, the enabling title is considered finalized without conditions.

The regulation (Article 8, paragraph 11) also establishes that the authorization will expire if the work is not initiated within one year from the completion of the PAS or if the construction is not completed within three years from its start.

Among the new construction interventions listed in Annex B – Section I, examples include:

Solar thermal plants with a thermal power of up to 10 MW, dedicated to industrial processes.

Photovoltaic solar plants under 10 MW, whose modules are installed as replacements for building roofs where asbestos or Eternit has been completely removed.

2.3 Authorization Process (Article 9 – Annex C)

According to Article 9, interventions listed in Annex C will be subject to the single authorization procedure.

The proponent must submit a single authorization request via the SUER platform (namely the one-stop shop for renewable energy) to the competent regional authority—or the delegated entity—for plants with a capacity below 300 MW, or to the Ministry of the Environment and Energy Security for plants exceeding this threshold or for offshore plants.

Paragraph 1 specifies that for projects listed in Annex C – Section I, which are subject to regional environmental impact assessment, Article 27-bis of the Environmental Code (PAUR) applies. The deadline for completing the procedure under Article 27-bis must not exceed two years.

This category includes, for example:

  • Photovoltaic plants with a nominal capacity of 1 MW or more, up to 300 MW.
  • Wind power plants with a capacity of 60 kW or more, up to 300 MW.
  • Projects located in protected areas or within the Natura 2000 Network.

Regarding the timelines for the authorization procedure, the regulation distinguishes between:

  • Projects subject to environmental impact assessment (Article 9, Paragraph 6). For those projects the public notice required under Article 23 of Legislative Decree 152/06 must be published within 10 days of the completion of the documentation review or receipt of additional requested documents. Observations can be submitted within 30 days from the publication date. The conference of services must be convened within 10 days from the conclusion of the consultation process or from the receipt of any additional required documentation.
  • Projects not subject to environmental impact assessment (Article 9, Paragraph 5). For those projects the conference of services must be convened within 10 days from the completion of the documentation review or receipt of any required additions.

3. Conclusions

Legislative Decree 190/2024 appears to address the demands for simplification and efficiency in Italy’s renewable energy sector. The reduction in the number of administrative regimes, shorter administrative timelines, streamlining of the environmental impact assessment procedures, the tacit approval mechanism for the simplified enabling procedure, as well as the enhancement of digital infrastructure for submitting applications, are all innovations aimed at reducing bureaucracy and providing certainty for investors.

The new regulatory framework is therefore expected to facilitate the long-awaited energy transition in Italy, enabling the country to achieve both the goals outlined in the National integrated energy and climate plan ( Piano Nazionale Integrato per l’Energia e il Clima – PNIEC) and, in the long term, the objectives set at the European level.

In the coming months, it will be crucial to observe how the Regions will adapt to the principles established by the new decree. The decree, in fact, allows them to further simplify administrative procedures, including the possibility of raising the power thresholds set in Annexes A and B.

At the same time, two key deadlines must be awaited:

  • May 21, 2025: To understand how GSE will map the national territory, identifying the potential and available areas for installing renewable energy production plants.
  • February 21, 2026: To determine how each region and autonomous province will adopt, based on GSE’s mapping, a Plan for Identifying Acceleration Zones for Land-Based Renewable Energy Plants.