Renewable energy sources: Italian authorization procedures for the installation of plants

July 4, 2024

Authors: Claudio Palmieri & Chiara Cremona

Renewable energy sources - authorization procedures
Renewable energy sources – authorization procedures

1. Identification of suitable surfaces and areas

In order to accelerate the country’s sustainable growth path in line with the European objectives of complete decarbonization by 2050, the installation of renewable energy plants requires, according to Article 20 of Legislative Decree No. 199 of November 8, 2021, “on the promotion of the use of energy from renewable sources,” the identification of suitable surfaces and areas. Article 20 delegates to one or more inter-ministerial decrees the establishment of uniform principles and criteria for identifying suitable and unsuitable surfaces and areas for the installation of renewable energy systems with a total capacity at least equal to that identified as necessary by the National Energy and Climate Plan (NECP) for achieving renewable energy development objectives.

To this end, the relevant Ministries, in agreement with the Regions, reached an agreement on June 7 2024 on the draft Ministerial Decree or MD, which will soon be published. According to Article 1, paragraph 1, letter a) of the MD, one of the purposes of the decree is to allocate among Regions and Autonomous Provinces the national target by 2030 of an additional capacity of 80 GW from renewable sources compared to December 31, 2020.

This capacity is necessary to achieve the objectives set by the NECP and to meet the new objectives resulting from the implementation of the European “Fit for 55” package, also in light of the subsequent “Repower EU” package.

Furthermore, Article 1, paragraph 2 states that the Regions, ensuring appropriate involvement of local authorities, shall identify within their respective territories:

  • suitable surfaces and areas;
  • unsuitable surfaces and areas, to be identified according to the methods established in paragraph 17 and Annex 3 of the guidelines issued by the Ministry of Economic Development on September 10, 2010, and subsequent amendments and integrations;
  • ordinary surfaces and areas, understood as surfaces and areas different from those identified in the previous points;
  • agricultural areas where the installation of ground-mounted photovoltaic systems is prohibited.

These surfaces and areas are identified by the Region through its own legislation within 180 days from the date of entry into force of the MD (Article 3 of the draft MD).

2. Authorization procedures

The installation of plants on suitable surfaces and areas is governed by Article 22 of Legislative Decree No. 199/2021, which states that in the authorization procedures, including those for the adoption of the Environmental Impact Assessment (EIA) decision, the competent authority in landscape matters provides a mandatory, non-binding opinion, and the deadlines for authorization procedures for plants in suitable areas are reduced by one third.

For ordinary surfaces and areas, the ordinary authorization regimes under Legislative Decree No. 28/2011 and subsequent amendments and additions apply.

Therefore, once the surfaces and areas where authorization regimes are determined, under the jurisdiction of the regions or autonomous provinces, the following apply:

AUTHORIZATION REGIMEPLANTS FALLING UNDER THE REGIMETIMES AND METHODS
Unique Authorization (Autorizzazione Unica)
– Article 12 Legislative Decree 387/2003 on the rationalization and simplification of authorization procedures
– Ministry of Economic Development Decree of September 10, 2010 – Guidelines for the authorization of renewable energy-powered plants
– Article 4, paragraph 2 bis Legislative Decree 28/2011 about promoting the use of energy from renewable sources
– Plants with a nominal power below 300 MW and above the following minimums for each renewable source:
Wind – 60 kW; Photovoltaic solar – 50 kW;
Biomass – 200 kW;
Landfill gas, residual gas from purification processes, and biogas – 300 kW
– Photovoltaic installations built in suitable areas with a nominal power exceeding 10 MW (Article 4, paragraph 2 bis Legislative Decree 28/2011)
The Unique Authorization includes environmental assessments, where required. The maximum deadline for the conclusion of the single procedure is 60 days, excluding the times provided for environmental assessment procedures under Title III of Part II of Legislative Decree No. 152 of April 3, 2006 (Environmental regulation), if necessary.
Simplified Authorization Procedure (Procedura Abilitativa Semplificata – PAS)
– Article 6 of Legislative Decree No. 28/2011 on the promotion of the use of energy from renewable sources
– Article 4, paragraph 2 bis of Legislative Decree No. 28/2011 – rules for specific cases of PAS use
– Ministry of Economic Development Decree of September 10, 2010, Guidelines for the authorization of renewable energy-powered plants, paragraphs 11 and 12

– Plants with a nominal power per renewable source below the limits set for the Unique Authorization regime;
– Plants identified in the paragraphs of the Ministry of Economic Development Decree of September 10, 2010:
• 12(2) – photovoltaic systems installed on buildings, with a total surface not exceeding the roof area
• 12(4) – small cogeneration plants up to 1,000 kWe, or up to 3,000 kWt of electric generation powered by biomass, landfill gas, residual gas from purification processes, and biogas
• 12(6) – removable anemometric towers in non-restricted areas for temporary measurement lasting more than 36 months
• 12(8) – plants powered by hydraulic sources
– Photovoltaic installations built in suitable areas with a nominal power up to 1 MW (Article 4, paragraph 2 bis of Legislative Decree No. 28/2011 about promoting the use of energy from renewable sources)
The Simplified Authorization Procedure must be submitted to the Municipality at least 30 days before the start of work. For the Simplified Authorization Procedure, the mechanism of tacit consent applies: if 30 days pass after submitting the PAS without any response or notification from the Municipality, work can commence.
Communication to the Municipality (Comunicazione al Comune – CAEL )
– Article 6, paragraph 11 of Legislative Decree No. 28/2011 on the promotion of the use of energy from renewable sources
– Ministry of Economic Development Decree of September 10, 2010, Guidelines for the authorization of renewable energy-powered plants, paragraphs 11 and 12
Small-scale installations (up to 200 kW) as specified in the paragraphs of the Ministry of Economic Development Decree of September 10, 2010:
• 12(1) – Photovoltaic installations adhering or integrated into the roofs of existing buildings;
• 12(3) – Biomass, landfill gas, residual gas from purification processes, and microgeneration biogas plants (up to 50 kWe) or installations in existing buildings that do not alter the building’s urban or structural profile and operate under Net Metering (SSP);
• 12(5) – Wind installations on the roofs of existing buildings with a total height not exceeding 1.5 meters and a diameter not exceeding 1 meter, not falling under the scope of the Code of Cultural Heritage and Landscape, and removable anemometric towers in non-restricted areas for temporary measurement lasting less than 36 months;
• 12(7) – Hydroelectric and geothermal power plants installed in existing buildings that do not alter the building’s urban or structural profile.
These are considered as activities falling under general building rights, and work can commence immediately after communication to the Municipality.
Declaration of Commencement of Works – Asseverated (Dichiarazione di inizio lavori asseverata – DILA)
– Article 6 bis of Legislative Decree No. 28/2011 on the promotion of the use of energy from renewable sources
– Article 4, paragraph 2 bis of Legislative Decree No. 28/2011 – rules for specific cases of Declaration of Commencement of Works – Asseverated use
– Existing RES installations requiring modifications and changes to the plant;
– Installations already authorized for modifications and changes to the project only;
– New photovoltaic installations with modules installed on roofs of rural buildings, productive use buildings, and residential buildings;
– Photovoltaic installations whose modules are installed to replace roofs of rural buildings and buildings where complete removal of asbestos has been carried out;
– Photovoltaic systems built in suitable areas with a nominal power up to 1 MW (Article 4, paragraph 2 bis of Legislative Decree No. 28/2011).
Work can commence immediately after notifying the Municipality with the Declaration of Commencement of Works – Asseverated.
General building rights – Article 6 of Presidential Decree 380/2001, Consolidated Text of Legislative and Regulatory Provisions on Building RegulationsPhotovoltaic installations carried out outside the historic center.Work can commence immediately after notifying the Municipality with the Certified Notice of Commencement of Activity (segnalazione certificata di inizio di attività – SCIA SCIA). Subject to compliance with municipal urban planning instruments and other sector-specific regulations on seismic, safety, fire prevention, health and hygiene, energy efficiency, and protection from hydrogeological risk.